HB2148
Proposed plat, site plan, etc.; time period for action by local planning commission.
Summary
As Introduced. Proposed plat, site plan, or plan of development or preliminary subdivision plat; time period for action
by local planning commission. Reduces from 45 days to 30 days the period of time that a local planning commission or other agent has to act on any proposed plat, site plan, or plan of development that it has previously disapproved after the first time such plat or plan has ... (More) been modified, corrected, and resubmitted for approval, and provides that such planning commission or other agent has within 15 days after the second or any subsequent time such plat or plan has been resubmitted for approval to act on such plat or plan. The bill makes similar changes to the review timelines for state agencies that review such plats. The bill also provides that, in any instance in which an initial review by a locality determines that the resubmitted application contains solely technical changes requiring less than 60 minutes of review, a locality's approved agent shall approve such application within five business days. The bill further provides that if a local planning commission has the responsibility of review of preliminary subdivision plats and conducts a public hearing, it shall act on the proposed preliminary subdivision plat within 35 days, rather than the current 45 days, after receiving approval from all state agencies. (Less)-
Bill History
- 01/07/2025 - House: Prefiled and ordered printed; Offered 01-13-2025 25104264D
- 01/07/2025 - House: Referred to Committee on Counties, Cities and Towns
- 01/20/2025 - House: Assigned CCT sub: Subcommittee #3
- 01/22/2025 - House: Placed on Counties, Cities and Towns Agenda
- 01/24/2025 - House: Subcommittee recommends laying on the table (5-Y 3-N)
- 02/04/2025 - House: Left in Counties, Cities and Towns